8. Cost of the Program.
An index of the magnitude of the effort now being made is
afforded by comparison of the level of Air expenditure in successive
financial years, as follows:-
Million.
1933 (pre-Expansion) .... 16 3/4
1934 (Scheme A) ........ 17 3/4
1935 (Scheme C) ......... 27 1/2
1936 (Scheme F) ......... 50
1937 .................... 81 3/4*
1938 (Scheme L) ......... 126 1/2 (estimated)
1939 (Present Scheme)... 208 1/2 (estimated)