S E C R E T APPENDIX "C" PRODUCTION POOL 1. Problem. To determine the implications of moving landing craft from the Production Pool: a. To ROUNDUP. b. To NORTH PACIFIC. c. To CENTRAL PACIFIC. d. To S0UTH-SOUTHWEST PACIFIC. e. To ANAKIM. 2. Basic data. a. LST's require 50 days fitting out and shakedown; sailing port - NEW 0RLEANS. b. LCI(L)'s require 35 days fitting out and shakedown; sailing port -HAMPTON ROADS. c. LCT(5)'s and smaller types are assembled at various East and West COAST ports. Their flow from U. S. depends entirely on shipping available. 3. To ROUNDUP. a. Time required in weeks. Type F/O & Shakedown Transit Assembly Train(l) Total LST 7 4 (2) - 3 14 LCI (L) 5 2 - 3 lO LCT(5) - 2 1 3 6 Shipborne - 2 1 3 6 NOTES: (1) Training time allowed after arrival destination. (2) One 3-day stop enroute for fuel and provision. b. Conclusion. Latest dates of allocation which will meet ROUNDUP target date are: - 18 - |