S E C R E T
LST - late December 1943
LCI (L) - mid-January 1944
LCT(5) and other
shipborne craft* - mid-February 1944
* Assuming shipping is immediately available.
4. To NORTH PACIFIC.
a. Assumption.
An operation to capture KISKA will be undertaken.
b. Time required in weeks.
Type F/0 & Shakedovn Transit(2) Assembly Train (1) Total
LST 7 6.5 - 3 16.5
LCL(L) 5 5 - 3 13
LCT(5) - 1.5 (3) l 3 5.5
Shipborne - 1.5 (3) 1 3 5.5
NOTES: (1) Training to be conducted on West Coast, U. S.
(2) NEW ORLEANS-SAN FRANCISCO-DUTCH HARBOR, includes 1
week for assembly of convoy on West Coast.
(3) Assuming departure SAN FRANCISCO and shipping immediately available.
c. Conclusion.
To meet any target date selected, allocations of types
of craft Shown above must be made as indicated in the table.
Decision has not been made as to types required.
5. To CENTRAL PACIFIC.
a. Assumption.
(1) LST's for MARSHALL ISLANDS campaign must be provided
from Production Pool.
(2) Target date for departure from PEARL HARBOR to
execute MARSHALL ISLANDS campaign is 1 April 1944.
b. Time required in weeks.
Type F/O Shakedown Transit (1) Train Total
LST 7 5 3 15
NOTE: (1) NEW ORLEANS-SAN DIEGO PEARL HARBOR, include one
3-day period for fuel and provisions.
- 19 -