S E C R E T
c. Conclusion.
If LST's are to be used from Production Pool, they must
be allocated in mid-December 1943.
6. To SOUTH-SOUTHWEST PACIFIC.
a. Assumption.
Replacement landing craft must be in the SOUTH-SOUTHWEST
PACIFIC by the time landing craft diverted to ANAKIM departs.
b. Time required in weeks.
Type F/O & Shakedown Transit (1) Assembly Train Total
LST 7 7 (1) - 3 17
LCI (L) 5 6 (2) - 3 14
LCT (5) - 3.5 (3) 1 3 7.5
Shipborne - 3.5 (3) 1 3 7.5
NOTES: (1) NEW 0RLEANS-PANAMA-BORA BORA-NOUMEA, includes two
3-day periods for fuel and provision.
(2) HAMPTON ROADS-PANAMA-BORA BORA-N0UMEA, includes two
3-day periods for fuel and provision.
(3) SAN FRANCISC0-NOUMEA and shipping is immediately available.
c. Conclusion.
Landing craft from the Production Pool to replace any
diverted from the SOUTH-SOUTHWEST PACIFIC to ANAKIM must be
allocated as follows:
LST - shoud have been made in mid-April, 1943
LCI (L) - should have been made in early May, 1943
LCT(5 ) and
Shipborne - must be made in late June, 1943
7. To ANAKIM.
a. Time required in weeks.
Type F/O & Shakedown Transit Assembly Train Total
LST 7 8 (1) 3 18
LCI (L) 5 6 (2) 3 14
LCT (5) - 6 (2,3) 3 9
Shipborne - 6 (2,3) 3 9
- 20 -